Scheduled Power Interruption (January 16, 2021)

Date: JANUARY 16, 2021 SATURDAYTime: 8:00AM - 5:00PM


Reason/s of Interruption:
1. To conduct Phase Four (5) of reconductoring of Three (3) Phase Primary line from #0/2 Bare Wire ACSR to #4/0 Bare Wire ASCR starting from Poblacion, Tabina C4 Structure bearing the pole number of DSB 1004 with estimated circuit kilometers of 0.779km.
2. To continue reconductoring the remaining Phase C conductor located at Barangay Abong-Abong, Tabina, 2.220 circuit kms.
3. To finish reconductoring the remaining Phase A Conductor, 1.032 circuit kms. located at Barangay Culabay, Tabina
4. Replacement of insulators from porcelain to polymer

Affected areas:
• Entire municipality of TABINA

PITOGO
• Barangay Tongao

• Barangay Matin-ao
• Barangay Limbayan
• Barangay Punta Fletcha
• Barangay Malim
• Barangay Upper Panikian

As a safety precaution, please always consider the power lines energized during the power interruption. Power will be immediately restored upon completion of the scheduled works. Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.

Thank you.